Implement

ERP Implementation Lifecycle: Complete Guide

3 min read ·

The ERP Implementation Lifecycle

Successful ERP implementation follows a structured lifecycle. Whether you're implementing SAP, Dynamics 365, or Odoo, the fundamental phases remain the same. This guide walks through each phase with practical advice for manufacturing companies.

Phase 1: Project Initiation & Planning (Weeks 1-6)

This phase sets the foundation. Get it wrong, and everything else suffers.

Key Activities: - Establish project governance (steering committee, project manager, key users) - Define scope, objectives, and success criteria - Build the detailed project plan with milestones - Conduct current-state process mapping - Begin master data assessment and cleansing strategy

Critical Success Factors: - Executive sponsor actively participates in steering committee (not just signs off) - Key users committed at minimum 20% of their time - Scope is documented and signed off — changes go through formal change control - Realistic timeline that accounts for your team's availability

Common Pitfalls: - Underestimating the data cleansing effort (plan for 30-40% of total effort) - Not involving shop floor users early enough - Trying to replicate every existing process in the new system

Phase 2: System Configuration & Development (Weeks 4-16)

This is where the system takes shape. Configuration decisions made here determine how the system works for years.

Key Activities: - Configure organisational structure (legal entities, plants, warehouses, work centres) - Set up master data templates and begin data loading - Configure core modules: MRP, production planning, inventory, purchasing, quality, finance - Develop integrations (CAD/PLM, MES, e-commerce, banking) - Build reports and dashboards

Manufacturing-Specific Decisions: - BOM structure: How many levels? Phantom assemblies? Configurable BOMs? - Routing complexity: Standard vs. alternative routings? Subcontracting? - Costing method: Standard cost vs. actual cost vs. average cost? - MRP parameters: Safety stock, reorder points, lot sizing rules, planning horizons - Quality integration: Inspection at receipt, in-process, final? Automatic vs. manual?

Configuration Principle: Configure before customise. Every customisation adds cost to every future upgrade. Challenge "we've always done it this way" — the ERP's standard process may be better.

Phase 3: Testing (Weeks 12-20)

Testing is where most manufacturing ERP projects either prove their value or reveal their gaps.

Testing Layers: 1. Unit Testing — Each configured process works individually 2. Integration Testing — End-to-end process flows (order-to-cash, procure-to-pay) 3. Data Migration Testing — Migrated data is complete and accurate 4. User Acceptance Testing (UAT) — Real users perform real scenarios 5. Performance Testing — System handles expected transaction volumes

Manufacturing Test Scenarios to Never Skip: - Full production order lifecycle (plan → release → issue materials → report → close) - MRP run with realistic demand and supply data - Quality inspection with pass/fail outcomes - Month-end close with WIP valuation - Multi-level BOM explosion

Phase 4: Go-Live Cutover (Weeks 18-22)

The cutover period is the most intense 2-4 weeks of the entire project.

Go/No-Go Decision: 2 weeks before go-live, assess against objective criteria: - All critical processes tested and signed off - Data migration rehearsal completed successfully (minimum 3 rehearsals) - Training completed for all user groups - Support plan and escalation procedures in place - Rollback plan documented and tested

Cutover Activities: - Final data migration (inventory counts, open orders, open POs, GL balances) - System validation and reconciliation - User access provisioning - Communication to all stakeholders - Parallel running (if applicable)

Phase 5: Hypercare & Stabilisation (Weeks 22-30)

The first 30 days after go-live require intensive support.

Hypercare Structure: - Week 1-2: On-site support, daily stand-ups, rapid issue resolution - Week 3-4: Transition to remote support, issue severity classification - Month 2-3: Optimisation, performance tuning, process refinement

Issue Severity: - Critical (4-hour response): System down, production stopped - High (8-hour response): Major process blocked, workaround possible - Medium (24-hour response): Process inconvenience, workaround exists - Low (backlogged): Enhancement, minor cosmetic issue

After Go-Live

Implementation doesn't end at go-live. The first 90 days determine long-term success. Read our guide on the First 90 Days After ERP Go-Live.

Need Expert Help?

PPEFIX LTD provides hands-on ERP implementation consulting tailored to manufacturing SMBs.

Get in Touch

We use essential cookies to make this site work. Click "Accept All" to also enable anonymous analytics (no IP tracking). Privacy Policy

ERP.guide AI Assistant
Question limit reached (/). Refresh to start a new session.

/ questions used